| Class schedule | HW assignments (Including preparation and review of the class.) | Amount of Time Required | |
|---|---|---|---|
| 1. | ・Orientation ・Overview of Construction Work (Process, Organization, Documentation) |
120minutes | |
| 2. | ・Social norms concerning building construction (laws, specifications, standards, etc.) ・Trends in Japan's architectural history and the flow of building production ・Architectural projects, procurement, and contracts ・Communication and accumulation of building production information (IT implementation, BIM adoption, etc.) |
180minutes | |
| 3. | ・Construction Preparation ・Fundamentals of Construction Management Planning |
180minutes | |
| 4. | ・Preparation of construction management plans (quality control, schedule management, safety management, cost management, environmental
management) ・Construction management plan preparation (quality control, schedule control, safety control, cost control, environmental control) |
180minutes | |
| 5. | ・Preparation of construction management plans ・Notifications and neighborhood coordination ・Operation and setup of work sites |
180minutes | |
| 6. | Temporary Construction ・Preliminary surveys, standard setting ・Scaffolding, temporary structures, lifting and transport machinery |
180minutes | |
| 7. | Earthwork ・Soil investigation, soil improvement ・Excavation, retaining walls, water treatment ・Pile work, foundation work |
180minutes | |
| 8. | Reinforced Concrete Construction ・Overall Construction Flow ・Reinforcement Work, Reinforcement Work Management |
180minutes | |
| 9. | Reinforced Concrete Construction ・Formwork construction, formwork construction management |
180minutes | |
| 10. | Reinforced Concrete Construction ・Concrete Work (Ordering, Receiving, Transporting, Placing, Curing) ・Management and Inspection of Concrete Work |
180minutes | |
| 11. | Exterior Wall Construction ・Precast Concrete Construction ・ALC Panel Construction ・Tile Construction |
180minutes | |
| 12. | Steel Frame Construction ・Work Processes, Inspections ・Structural Work (Fabrication, Processing, Erection of Components) ・Various Construction Methods, Fireproof Cladding |
180minutes | |
| 13. | Woodworking ・Construction methods for wooden structures, carpentry work, framing work ・Construction management for wooden structures |
180minutes | |
| 14. | Recent Topics in Construction Production Final Exams and Explanations |
370minutes | |
| Total. | - | 2650minutes |
| ways of feedback | specific contents about "Other" |
|---|---|
| Feedback outside of the class (ScombZ, mail, etc.) |
| Work experience | Work experience and relevance to the course content if applicable |
|---|---|
| Applicable | Faculty members who have been involved in drafting legal frameworks, technical standards, and specifications related to building production at administrative agencies and public research institutions will conduct the lectures. |